Pratt & Whitney
•
2020
Carlisle Construction provided an FFP proposal and was selected to expand the existing Pratt-Whitney manufacturing plant by adding a 14,000 SF building designed to house a new disc press. The construction includes: Removal of existing pre-cast concrete panels, protection of existing plant to avoid any inhibition of ongoing manufacturing, installation of concrete pits, walls, and trenches, rerouting of underground utilities; extension of plant process utilities and piping; installation of structural steel framing; supplying and installing switchgear; and new building envelope on a restrictive shortened timeline to meet the press arrival date.
This is some text inside of a div block.